Evaluation of VDOT Chip Seal Practices: Materials and Design
Project No: 118820
Target Completion Date: August 31, 2023 Pavements
About the project:
There have been considerable research efforts conducted, in recent years, at local and national levels to investigate the effect of material characteristics as well as design techniques on the performance of chip seals. In addition, with the advancement of technology, new materials and additives have been introduced into the construction market with the goal of enhancing the performance of chip seals. Despite these advances, and the long history of chip seal use on its roadway network, the Virginia Department of Transportation (VDOT) has not undertaken a thorough review of its chip seal practices in more than 25 years. The objective of this research study will be to evaluate VDOT’s single layer (single layer and modified single layer) chip seal practices from a materials characterization and design perspective.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Mass Concrete Mixtures Optimized for Temperature Control and Workability
Project No: 117779
Target Completion Date: October 31, 2023 Pavements
About the project:
Mass concrete elements are usually heavily reinforced and subject to large thermal change as the concrete cures. The definition of mass concrete is generally based on the minimum dimension of the element but is more complicated because of the many factors involved. High heat retention in mass concrete causes differential and high temperatures that can result in detrimental cracks. In some applications of mass concrete, high strengths or early strengths are needed, requiring increases in cementitious material contents beyond the usual low amount of cementitious materials needed in mass concrete to keep the temperature from rising too high during cement hydration. Typically, concretes with regular consistency measured by slump test are used in mass concrete elements. However, congestion of the reinforcement in the element combined typically with geometric and placement constraints require concretes with high flow rates, as in self-consolidating concrete (SCC). Such concretes generally have high cementitious material contents for flowability and stability. There is a conflict in the amount of cementitious materials between mass concrete which requires low cementitious contents to control temperature rise and the use of high cementitious contents for early or high strengths and high workability. The cementitious material contents include supplementary cementitious materials, fly ash and slag cement, for durability and to reduce portland cement contents for temperature control. The objective of this study is to investigate and optimize mass concrete mixtures with regards to temperature control and high workability. Also, the definition of mass concrete will be refined in ways that are helpful to VDOT in taking precautions to avoid problems that can arise during placement and curing.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Other Investigators
- Mary Sharifi
I-95 Variable Speed Limit Evaluation Phase 2
Project No: 122766
Target Completion Date: February 28, 2024 Pavements
About the project:
The Virginia Department of Transportation (VDOT) is operating a variable speed limit (VSL) system on I-95 northbound between mileposts 115 and 130, south of Fredericksburg. The goal of the VSL system is to improve both safety and operations on this congested section of highway by encouraging speed harmonization, more uniform speed selection, dampening the effects of shockwaves, and providing advance warning of congestion. This project will continue the evaluation of the safety and operational impacts of the VSL system to determine benefits during the first year of operations. Performance measures will include changes in crashes, travel time reliability, delay, throughput, and speed compliance. The overall benefit-cost ratio of the system will be examined as well.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Developing Long-term Aging Protocols for Cracking Performance Evaluation of Asphalt Mixtures in Virginia
Project No: 122013
Target Completion Date: January 31, 2025 Pavements
About the project:
The Virginia Department of Transportation (VDOT) currently requires the use of the Indirect Tensile Cracking Test (IDT-CT) as specified in ASTM D8225-19 in its Balanced Mix Design (BMD) specification to assess the cracking susceptibility of dense-graded asphalt surface mixtures (SM) with “A” (PG64S-22) and “D”(PG64H-22) designations (i.e., 0 to 3 million equivalent single axle load [ESAL] range for A mixtures and 3 to 10 million ESAL range for D mixtures). A current performance criterion requiring a minimum cracking tolerance (CT) index of 70 was recommended to alleviate the cracking susceptibility of the asphalt mixtures based on extensive mixture testing. This CT index was determined based on testing of compacted specimens from reheated plant-produced asphalt mixtures. Although the current cracking testing protocol and its threshold value (i.e., CT index of 70) in VDOT’s BMD specification is indicative of the cracking performance of asphalt mixtures, it does not account for how the performance of asphalt mixtures throughout the service life is affected by oxidative aging (i.e., as it experiences long-term aging). Thus, laboratory evaluation of the long-term oxidative aging characteristics of asphalt mixtures is essential to ensure that the asphalt mixtures within the pavement structures continue to perform adequately throughout their service life. The objective of this research is twofold: (I) to develop practical long-term aging protocols for asphalt SMs with A and D designations that can be used in mix design verification and production of asphalt mixtures for quality control and acceptance purposes; and (II) to develop preliminary performance criteria for CT index for the to-be-developed long-term aging protocols.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Other Investigators
- Ellie Hajj
Pilot Application of Floodcast Technology in a District
Project No: 124060-RC00161
Target Completion Date: October 31, 2024 Pavements
About the project:
VDOT seeks to explore how to enhance its capability to anticipate threats to system level service and customer mobility, namely flood impacts on transportation assets.
Through an environmental scan, VDOT will be able to understand such existing operational and emergency management systems being used by other DOTs and MPOs to provide resilience in their transportation network. Alongside the scan, this effort will document VDOT's flood threat monitoring, assessment, and response needs from an operational perspective.
Objectives:
- Provide VDOT with an understanding of current state of the practice for forecasting flood impacts at transportation assets, with peer DOT organizations.
- Systematically solicit and compile requirements for a flood warning capability from a representative cross-section of VDOT District and HQ operations, maintenance, and emergency management staff.
- Using state of the practice information gathered and VDOT requirements develop a summary recommendation.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Data-Driven Decision-Making Framework for Inspection of Bridge Decks
Project No: 118730
Target Completion Date: May 31, 2024 Pavements
About the project:
Routine inspections as per National Bridge Inspection Standards regulations provide rough estimates of bridge deck conditions at least every 24 months. Being primarily visual, this information does not provide in-depth information needed for maintenance decisions. So, when severe deterioration is suspected, more extensive inspection approaches are pursued. However, very little guidance exists for when to trigger further inspection and what methods to employ. In addition, rapid growth in technology has made available several affordable non-destructive evaluation techniques with reduced traffic impacts. Similarly, no guidance exists on when to apply them and what value they can provide. This study seeks to develop a methodology to improve routine inspections for consistency, evaluate available technologies to better inform inspection strategies, and develop a preliminary data-driven framework for decision-making regarding bridge inspection levels.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Other Investigators
- Richard Weyers
Pavement Friction Management Program Implementation (Phase 3) - District-Level Deploymen
Project No: 118900
Target Completion Date: April 30, 2024 Pavements
About the project:
This is the third phase of research designed to implement pavement friction management (PFMP) with the goal of minimizing crash-related fatalities and serious injuries. This final-phase project will provide the transitional support necessary for a statewide deployment of the developed safety analysis and treatment recommendation framework as documented in the Phase 1 and 2 reports. Phase 3 will work with the data collected in Phase 2 in each District and involve: further demonstrating the technology; uploading the data collected to the pavement management system (PMS); training the district personnel on the use of the data; and developing written guidelines for implementing project-level and network-level CFM.
Project Team
Principal Investigators
Co-Principal Investigators
Project Manager
Project Monitor
Members
Other Investigators
- Edgar de Leon Izeppi, Gerardo Flintsch
Last updated: April 4, 2024
